Bolivar Production


 

Dia Bras

2009
2008
2007
2006
2005
 
Tons. mined 88,254 129,700 122,967 96,576 50,371
Tons. milled 89,577 126,489 127,106 96,576 50,371
Tons. milled per day 256 361 363 276 155
Copper grade 1.82% 1.65% 1.49% 2.07% 1.89%
Zinc grade 9.98% 8.00% 6.94% 10.76% 8.07%
Copper recovery 87.40% 83.40% 81.33% 80.64% 74.36%
Zinc recovery 88.79% 87.15% 86.49% 91.92% 85.82%
Copper conc  produced ( tons) DMT 5,069 6,454 5,635 5,507 2,608
Zinc conc produced ( tons). DMT 13,696 15,355 13,574 16,182 6,218
Cu Prod'n (lbs.) 3,122,783 3,854,688 3,528,778 3,507,114 1,560,686
Zn Prod'n (lbs.) 17,686,209 19,077,613 17,028,843 20,903,371 7,690,886
AV Cu price LME 2.33 3.15 3.23 3.01
AV Zn price LME 0.75 0.85 1.47 1.38